S N Engineering
Cement Grinding Terminal – Sheerness Docks
Burden Bros Construction Ltd delivered the complete civils package for a cement grinding terminal located within Sheerness Docks, supporting the construction of a major industrial facility with a capacity of 500,000 tonnes per annum.
Client
S N Engineering
Location
Sheerness Docks
Project Type
Cement Grinding Terminal
Scope
Civil Engineering & Piling Works
Date
July 2025
Project Overview
The complete civils package, located within Sheerness Docks, comprised the design and construction of a cement grinding terminal with a capacity of 500,000 tonnes per annum.
The works included 328 steel-driven piles, reinforced concrete pile caps and ring beams, weighbridge supports and hardstanding access to support the site and its four proposed silos.
The project required careful coordination across a live dockside environment, with works delivered to support the construction of a large-scale industrial processing facility.